ManufacturingSpacesTechGovernance
New plant headquarters delivered as one programme
- Background
- A 900-employee auto component group consolidating four sites into one campus.
- Challenge
- Parallel vendors for interiors, IT and compliance created a nine-month schedule risk.
- SJAIN solution
- Spaces delivered the 68,000 sq ft campus, Tech deployed the plant data platform, Governance rebuilt statutory reporting.
- Outcome
- Occupied 11 weeks early, 22% lower cost per seat and a single compliance dashboard for the board.
- Lesson learned
- Sequencing interiors and technology on one plan removes the most expensive form of rework.