Background
A European engineering group establishing its first India capability centre.
Challenge
No local team, an aggressive hiring plan and a fixed board-approved opening date.
SJAIN solution
Spaces ran site selection, design and build; Governance handled entity setup and registrations.
Outcome
400 seats operational in 19 weeks with facility management transitioned to a managed contract.
Lesson learned
Entity approvals, not interiors, are usually the critical path on a first-site entry.