A three-state expansion run from one programme office
Eleven facilities, one warehouse management rollout and one compliance model, sequenced by a single programme office.
11
Facilities opened
14 mo
Programme duration
3
States covered
All case studies
- Background
- A third-party logistics operator opening 11 facilities across three states in 14 months.
- Challenge
- Every state had different registrations, and each facility was procuring technology separately.
- SJAIN solution
- The group consulting office sequenced the portfolio; Tech standardised warehouse systems, Spaces delivered the facilities, Governance handled state registrations.
- Outcome
- All 11 sites live within plan and a repeatable opening playbook now used for every new facility.
- Lesson learned
- Expansion is a supply chain problem before it is a real estate problem.
Related work
Other engagements worth reading
Integrated consulting · Manufacturing
New plant headquarters delivered as one programme
Four sites consolidated into one campus with interiors, plant data platform and statutory reporting delivered on a single plan.
Governance · HealthcareMulti-site clinic network prepared for institutional funding
Control environment, virtual CFO function and a repeatable clinic template built ahead of a Series B round.
Technology · Financial ServicesRegulated lender modernised without a compliance gap
Loan origination and analytics re-platformed under continuous controls testing, with 12 branches refitted in parallel.
Explore related filters